Issue 5     November 2000   
363-206-208
Equipment and Front Access Cable Installation for the DDM-2000 OC-12 Multiplexer
Lucent Technologies - Proprietary
See Notice on first page
Planning
The DDM-2000 OC-12 may be mounted as follows: 
a. Mounted in network bay frame. The recommended network bay frame for front 
access is the ED-8C500 or ED-8C800. Refer to Figures 3-4, 3-5, and 3-6 on 
Pages 3-49 through Page 3-51 for DDM-2000 OC-12 placement in a network 
bay frame. 
b. Miscellaneously mounted, meeting requirements in “Equipment Installation 
Considerations”.
Equipment Installation Considerations
Detailed network bay frame installation information is contained in ED-8C727-10, 
“Typical Bay Arrangements”. The information in this paragraph is of a general nature. 
The equipment listed below has the following height dimensions: 
Each DDM-2000 OC-12 shelf installed must have an air gap of at least 3.0 inches 
between the bottom of the DDM-2000 OC-12 shelf and the equipment (or bay frame if 
the shelf is installed at the bottom of the bay) below it. 
A fan shelf and heat baffle are required above each DDM-2000 OC-12 shelf. Refer to 
the bay layout shown in Figure 3-5 on page 3-50 and Figure 3-6 on page 3-51. 
A heat baffle must be installed below the DDM-2000 OC-12 if any heat generating 
equipment is located below the DDM-2000 OC-12. 
NOTE:
DDM-2000 OC-12 heat baffles must be used where required. There is no equiv-
alent air gap. 
ED-8C727-30, G1 DDM-2000 OC-12 Shelf 14.0 inches
ED-8C733-30, G1 Heat Baffle 4.0 inches
ED-8C733-30, G8 DDM-2000 OC-12 Fan Shelf 4.0 inches