2.3 Preparation for Measurement
HA-8190V 2-13
b Close the transparent cover.
Be sure to close the cover to prevent accidental operation.
“Initializing ...”
The parameter settings will be read and the mechanical
sections will be initialized.
“Warming up ...”
The instrument is adjusting internal temperature to enable
measurement.
Measurements can be reserved.
The main menu lists only the options available during
warm-up.
“Removing air ...”
The tubes are being filled with eluents and hemolysis washing
solution to remove air in the tubes.
Measurements can be reserved.
The main menu lists only the options available during priming.
“Ready for measurement”
The standby screen will appear, indicating that the instrument
is now ready for measurement.
REFERENCE:
Indications and functions available during warm-up and priming, and when the instrument is on standby are given
below.
Message “Warming up ...” “Removing air ...” “Ready for measurement”
Status Warm-up Priming Standby screen
Icon
Flash in light green Flash in light green Continuously lit in light green
Menu operation *Only available options are listed on the menu.
When press : Measurement is reserved (measurement starts when warm-up
and priming are complete).
Measurement starts
immediately.
REFERENCE:
The blue icon flashes when a measurement has been reserved. To cancel the reserved measurement,
press .
The orange icon lights while final processing is being performed after measurement.
The gray icon flashes if no user has logged into the instrument with an operator ID. This icon lights
continuously while the user is operating the instrument from the menu screens or being prompted to log in with
an operator ID.