OPERATION
103
1. Use the PREV & NEXT keys or
scroll wheel to move to the GR
CONT. field.
2. Press the ENTER soft-key followed
by using the scroll wheel to select
an option. When TIME is selected,
define a G-TIME by using the
arrow keys and the scroll wheel.
KEY
Test cannot be proceeded to until
continuity connection is well established.
TIME
After continuity connection is wired,
test will be started after the set time
duration (000.2 ~ 999.9 sec) is reached.
Note that the set time will recount if
continuity connection is disrupted amid
the set time duration.
3. Press the ENTER soft-key to
confirm the setting
GR CONT.
Displays
KEY
Test is stopped with GR CONT message