46 Keysight N9038A MXE Service Guide
Boot Up and Initialization
Potential Problems During Boot Process
Figure 2-4 A7 Midplane Board - Test Point 518/POWER_ON_L LED
5. Turn the instrument power on from the front panel On/Off button and view
the status of the POWER_ON_L LED, as shown in Figure 2-4.
Does the POWER_ON_L LED come on? (Test Point 518 should also go to
0 VDC)
If yes:
Proceed to step 6.
If not:
Verify the connection between the front panel On/Off
switch and the A4 Processor assembly by checking the
status of the POWER_SW_L control line when the front
panel On/Off button is both pressed and released. This can
be monitored by measuring the voltage at Test Point 520,
as shown in Figure 2-5.
With the On/Off button released this should measure a TTL
high level, and with the button pressed it should measure a
TTL low level. The A4 Processor board assembly provides
the voltage and the switch on the front panel pulls it low
when it is pressed.

Table of Contents

Other manuals for Keysight N9038A

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Keysight N9038A and is the answer not in the manual?

Keysight N9038A Specifications

General IconGeneral
BrandKeysight
ModelN9038A
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals