CAUTION!
Maintenance of metering pumps
Regular maintenance is required to ensure that the equipment functions
properly in the long term.
Dosing pumps may only be maintained by trained and authorised persons.
Interval Maintenance work
1/2 yearly
Standard maintenance of the pump.
Refer to the pump documentation for maintenance instructions (
Ä
Chapter 10.3 ‘Maintenance of
metering pump EMP III E00, E10’ on page 68 and
Ä
Chapter 10.4 ‘Maintenance of TCD turbo
pump’ on page 71 and
Ä
Chapter 1.1.1 ‘Further instructions’ on page 6 ).
Safety and functional testing of the complete system
(Leak-tightness of all components, replacing tubing and pipelines, where needed)
Annually
When installing a backflow preventer, check it to ensure that it is functioning properly.
Monthly
Maintenance of the pump if under a heavy load (for example, continuous operation)
Weekly
Visual checks
10.1 Carry out maintenance work
1.
Perform visual checks as described in
Ä
Chapter 8 ‘Start-up’ on page 63 .
2. Functional check of all installed components.
3. Check correct metering.
4. Check the metering head screws for tightness, as described in the enclosed pump
operating instructions.
5. Recalibration of the entire system via the 3/2 way valve.
6. Clean the electric cables in case of wetting by media