Driving
5.1 Before driving
5 - 2 3 302 736 en Operating manual
GMK4090
xx.xx.xxxx
2. When the main boom is resting on a dolly
All telescopic sections must be locked together.
The slewing gear is switched off;
à p. 11 - 118.
The boom floating position must be switched on;
à p. 6 - 13.
The slewing gear freewheel must be switched on;
à p. 6 - 12.
The boom pre-tensioning may be switched on;
à p. 6 - 14.
The houselock may be switched off;
à p. 11 - 16.
The superstructure must be unlocked;
à p. 11 - 14.
3. On the outriggers
All outrigger beams must be fully retracted and secured to prevent
extension;
à p. 12 - 46.
The outrigger pads are in the driving position;
à p. 12 - 53.
4. All mirrors for crane operation are folded in/removed;
à p. 12 - 153.
All spotlights are switched off and swivelled (if possible) in such a way
that no other drivers will be blinded by reflection;
à p. 11 - 128.
The lighting on the outrigger must be switched off;
à p. 12 - 45.
5. Anemometer, air traffic control light and camera system must be
removed:
à Anemometer and air traffic control light, p. 12 - 147,
à Camera on main boom, p. 12 - 154.