Commissioning and Diagnostics
6-59
ET 200S Distributed I/O System
EWA-4NEB 780602402-12
6.2.2 Commissioning and startup of the ET 200S o n PROFINET IO
Software requirements
Table 6-25 Software requirements for commissioning on PROFINET IO
Engineering software
used
Version Notes
STEP 7 As of Version 5.3
and ServicePack 1
You use HWCONFIG and the supplied device database
file.
Configuration software
for a different I/O
controller
You need the device database file of ET 200S.
Requirements for commissioning the ET 200S
Table 6-26 Requirements for commissioning the ET 200S on PROFINET IO
Prior Activity
See
1. I/O device installed Section 4
2. I/O device wired Section 5
3. MMC inserted; I/O device configured with device name
(configured and parameters set)
Section 6.2.1
4. Supply voltage switched on for I/O controller Manual for I/O controller
5. I/O controller switched to RUN mode Manual for I/O controller
Commissioning the ET 200S
Table 6-27 Steps for commissioning the I/O device
Step
Procedure See
1. Switch on the supply voltage for the I/O device. Section 8.6
2. Switch on the supply voltage for the load as necessary.