3.11 Checking the correct installation and configuration
# Step Action Reference
1
Switch on the
Metal Detector
Check that there are no Fault or Warning messages Display
2
Checking guards
Check that all guards have been installed correctly Installation manual
3
Starting the
transport system Check that the conveyor belt installation is stable, without
vibrations for the Metal Detector and that the belt does not rub
against the antenna or any other parts of the belt.
Start any machines in the line with the Metal Detector and
check there is no electrical and/or mechanical noise that might
generate false alarms by the Metal Detector.
Installation manual
Programming manual
-
Configuration-adv menu
4
Checking
performance
Set the detection parameters based on the product to be
inspected.
Programming manual
-
Autolearn menu
-
Autolearn-adv menu
-
Ejection menu
-
Configuration-adv menu
Check that the non-contaminated product passes through the
Metal Detector without generating alarm, in accordance with
the operating conditions.
In CEIA integrated systems, check that the product, passed
through with each of the test samples available, is ejected
correctly according to the methods provided.
5
Checking the
self-diagnosis
system and the
connection in
the line
Simulate all the possible fault conditions provided for the
system and check that the Metal Detector is programmed
correctly to guarantee the appropriate actions in the required
times at all times
Installation manual
Programming manual
-
Diagnosis managem.menu
-
Configuration-adv menu
At the end of the installation and checks, before commissioning the equipment, remove all keys
used to open the fixed guards, so that the normal operators do not have direct access to them.