SITE TEST PROCEDURE
F - 22
CUSTOMER COPY
PROVISIONAL ACCEPTANCE
The site acceptance test of the Model 7200 Antenna Control System is complete
except for the discrepancies as noted below. Control of the system is now
transferred to the customer. This discrepancy list is considered to be final.
Customer: _____________________ Location: ____________________________
Equipment: _____________________ Date: ____________________________
(Customer Representative)
______________________________________
(VertexRSI Representative)
______________________________________
Discrepancy List
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________

Table of Contents