Switch-on sequence
Parameter manual b maXX BM5800
Document No.: 5.16029.03 Baumüller Nürnberg GmbH
26
of 814
2.5
2.5 Switch-on sequence
The following overview shows the commissioning schematically. You will find the individ-
ual steps of the commissioning described in detail in ZPerforming the commissioning (us-
ing Axis 1 as an example)– from page 27.
Figure 8: Switch-on sequence
5800_0023_rev01.cdr
1
2
3
4
5
6
7
8
Switch on 24V
Turn on mains
Find notch position
Set speed
Enable motor rotation
Motor n=0
Turn off mains
Turn off 24V
Step