Commissioning
Parameter manual b maXX BM5800
Document No.: 5.16029.03
27
of 814
2
2.6 Performing the commissioning (using Axis 1 as an example)
Begin the commissioning after you have completed the preparations.
1 Connect the power supplies to the b maXX
(main power supply + control voltage).
2 Establish communication as described in ZPreparations– on page 18.
3 Start the ProDrive program (if it is not already running).
4 Then click on "Drive Manager" in ProDrive
Figure 9: ProDrive: Project tree for Drive Manager
Acknowledging
warnings/errors
5 "Acknowledge" any warnings/errors that may be present in the "Drive Management"
window (press the "Reset errors" button several times if necessary)
NOTE
Any queued error messages may result from the as yet incomplete parameter setting.
These errors cannot be acknowledged.