Appendix C - Step-by-Step Commissioning Procedures CPE Physical Site Installation
CPE Physical Site Installation
1. The CPE site installation procedure is similar to the CO site installation procedure.
2. If you configured the ML CO device according to CO Configuration - for Link
Verification, then the copper connectivity can be verified by ensuring the MLP and HSL
LEDs will be blinking or steady GREEN, indicating the modems of ML devices on CO
and CPE sites are synchronizing (blinking) or synchronized (steady). In case of using
auto-mode the MLP LEDs on CPE might not lit. In such case user may need to re-
calibrate the HSL from the CO site.
3. Optionally disable all unused MLP ports.
4. This completes the physical installation of the ML device in the Customer Premises /
Remote Terminal environment.