6.1.4 Powering On a Server
This topic describes how to power on a server.
Procedure
Step 1 Check that the power cables and ground cables of the upstream components of
the server are securely connected with correct polarity and in good contact.
Step 2 Ensure that the upstream input power supply is not connected. Use a multimeter
to measure the resistance between the upstream output power supplies and
between the working ground and the protection ground. It is required that a short
circuit not occur between output power supplies or between the working ground
and the protection ground.
Step 3 Turn on the switch for the upstream power supply of the server.
Step 4 Press the power button on the chassis of the server to power on the server.
NO TE
After the server is started properly, the button/indicator of its power switch is displayed
green.
Figure 6-1 Power button on the 2288X V5 server
iMaster NetEco
Device Installation and Commissioning Guide (Data
Center) 6 Adding Devices
Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd. 140

Table of Contents