Step 4 Connect the server power cables to the PDU2000.
NO TE
The server uses dual power supplies. Connect the two power cables to dierent PDU2000s.
Figure 3-8 Connecting server power cables
----End
3.3 Installing a LAN Switch
Procedure
Step 1 Determine the mounting holes for the LAN switch based on the network cabinet
device layout, adjust the guide rails or trays, and install
oating nuts.
Step 2 Install the mounting ears delivered with the LAN switch and secure the LAN
switch to the mounting bars in the front of the cabinet.
NO TE
This section describes only the installation method. The actual product appearance prevails.
iMaster NetEco
Device Installation and Commissioning Guide (Data
Center) 3 Installing Devices
Issue 02 (2021-05-12) Copyright © Huawei Technologies Co., Ltd. 22

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei iMaster NetEco V600R021C10 and is the answer not in the manual?

Huawei iMaster NetEco V600R021C10 Specifications

General IconGeneral
BrandHuawei
ModeliMaster NetEco V600R021C10
CategoryNetwork Hardware
LanguageEnglish

Related product manuals