S300 Expansion Enclosures CK721-A Installation and Operation
3-2 24-10349-8 Rev. B
This document contains confidential and proprietary information of Johnson Controls, Inc.
© 2012 Johnson Controls, Inc.
IMPORTANT
Observe the following precautions:
 It is important to follow the installation procedures described in this chapter very
carefully. Power wiring and grounding from the building to the S300 expansion
enclosures must only be performed by certified electricians. Failure to have
qualified professionals perform these functions can result in personal injury,
damage to a facility’s electrical system and other equipment, or damage to the
system and devices.
 Electronic components such as the printed circuit board assemblies used in the
S300 expansion enclosures are extremely static sensitive. To prevent
electrostatic discharge (ESD) damage, a properly grounded wrist strap must be
used at all times when handling the components. If a wrist strap is not available,
touch any part of the metal CK721-A cabinet prior to handling components to
discharge static electricity. It is advisable to avoid working on carpeted areas if
possible.
Tools Required
The following tools are required to install S300 expansion enclosures:
 Mounting tools such as a drill and anchors (depending on where you mount
the panels)
 Phillips screwdriver
 Small common screwdriver
 Standard wiring tools
 Hammer and punch
Sequence of Steps
Although each site configuration may differ and require different steps, the standard
steps required for installing S300 expansion enclosures are:
 Planning the installation
 Mounting the enclosures
 Installing the first level modules
 Wiring and configuring first level modules
 Installing the second level (stacked) modules
 Wiring and configuring second level modules
Planning the Installation
This section provides important information you will need when planning the
installation of an S300 expansion enclosure.