Pos: 109.92.9 / BA/Einstellunge n/Großpackenpr esse/Knoter/D oppelknoter/Einst ellung der Halt ekraft des Gar nhalters Doppel knoter @ 2 4\mod_1241416 439493_78.d ocx @ 243462 @ 4 @ 1
19.15.9.1 Setting the holding force of the twine retainer (6)
Fig.
210
The holding force has been preset ex works.
Note
The type and moisture content of baling material and its baling density as well as the tying
twine that is selected all require different settings, which have to be determined by trial and
error under actual working conditions.
To do this:
Loosen the counter nut (3)
Ensure stronger or weaker pre-tensioning of the twine retainer spring (2) with screw
(approx. half a turn)
Tighten the counter nut (3)
Note
The twine retainer should only clamp the twine securely enough so that it is not pulled out of the
twine retainer mechanism during the tying process. If the clamping effect is too great, it will tear
the twine into shreds.