Detailed description
2.4 Starting up the PLC program
Basic logic functions: PLC basic program solution line (P3 sl)
24 Function Manual, 11/2006, 6FC5397-0BP10-2BA0
2.4.7 Software upgrades
Software upgrade
Whenever you update the PLC or NCK software, always reset the PLC to its initial state first.
This initial clear state can be achieved by means of a general PLC reset. In case of this
resetting all the available blocks are deleted.
In normal cases, the new basic program is to be linked for a new NCU software version. The
basic programs blocks must be loaded into the user project for this purpose. No OB1, OB40,
OB82, OB86, OB100, of the FC12 and also of the DB4 should be transferred, if these blocks
are already present in the user project. These blocks may have been modified by the user.
The new basic program must be linked with the user program.
To do this, proceed as follows:
1. Generate the text or source file of all user blocks before copying the basic program.
2. Then copy the new basic program blocks to this machine project (for a description, see
Subsection "Application of basic program")
3. All user programs *.awl must then be recompiled in the correct order! (See also the
"Machine program" section.)
4. This newly compiled machine program must then be loaded to the PLC CPU using STEP
7.
However, it is normally sufficient to recompile the organization blocks (OB) and the instance
data blocks of the machine program. This means you only need to generate sources for the
organization blocks and the instance data blocks (before upgrading).
Overall reset
A description of how to perform a general PLC reset appears in the Installation and Start-Up
Guide. However, a general reset does not delete the contents of the diagnostic buffer nor the
node address on the MPI bus. Another possible general reset method is described below.
This method must be used when the normal general reset process does not work.
Proceed as follows:
No. Action Activation
1 Control system is switched off
2 PLC switch setting 3 (MRES) and switch control on
again or perform hardware RESET.
LED labeled PS flashes slowly.
3 Set PLC startup switch to position 2 (STOP) and
back to position 3 (MRES).
The LED labeled PS starts to flash
faster.
4 Set PLC start-up switch to setting 2 or 0.

Table of Contents

Other manuals for Siemens MCP 398C

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens MCP 398C and is the answer not in the manual?

Siemens MCP 398C Specifications

General IconGeneral
BrandSiemens
ModelMCP 398C
CategoryControl Systems
LanguageEnglish

Related product manuals