CHAPTER 11: METERING METERING FLEXANALOG PARAMETERS
D90
PLUS
LINE DISTANCE PROTECTION SYSTEM – INSTRUCTION MANUAL 577
PMU 1 POWER TRIGGER..........................
Asserted when the overpower trigger of Phasor Measurement
Unit 1 operates.
PMU 1 ROCOF TRIGGER...........................
Asserted when the rate of change of frequency trigger of
Phasor Measurement Unit 1 operates.
PMU 1 TRIGGERED.....................................
Asserted when the Phasor Measurement Unit 1 triggers. No
events or targets are generated by this operand.
PMU 1 VOLT TRIGGER ...............................
Asserted when the abnormal voltage trigger of Phasor
Measurement Unit 1 operates.
Phasor Measurement Unit one-shot operands
PMU ONE-SHOT EXPIRED .......................
Asserted after the one-shot operation executes.
PMU ONE-SHOT OP ...................................
Asserted upon one-shot operation.
PMU ONE-SHOT PENDING......................
Asserted while the one-shot operation is pending. That is, while
the present time is before the scheduled one-shot time.
Metering FlexAnalog parameters
The following metering FlexAnalog parameters (analog operands) are available for the
D90
Plus
. They are listed alphabetically by operand syntax.
Phasor Measurement Unit analog operands
PMU 1 Conf Ch ............................................
Metered configuration change counter value for Phasor
Measurement Unit 1
PMU 1 df dt ...................................................
Metered frequency rate of change value for Phasor
Measurement Unit 1
PMU 1 Freq....................................................
Metered frequency value for Phasor Measurement Unit 1
PMU 1 Num Triggers ................................
Metered number of triggers for Phasor Measurement Unit 1
PMU 1 Ia Mag...............................................
Metered phase A current magnitude for Phasor Measurement
Unit 1
PMU 1 Ia Ang................................................
Metered phase A current angle for Phasor Measurement Unit 1
PMU 1 Ib Mag...............................................
Metered phase B current magnitude for Phasor Measurement
Unit 1
PMU 1 Ib Ang................................................
Metered phase B current angle for Phasor Measurement Unit 1
PMU 1 Ic Mag...............................................
Metered phase C current magnitude for Phasor Measurement
Unit 1
PMU 1 Ic Ang................................................
Metered phase C current angle for Phasor Measurement Unit 1
PMU 1 Ig Mag...............................................
Metered ground current magnitude for Phasor Measurement
Unit 1
PMU 1 Ig Ang................................................
Metered ground current angle for Phasor Measurement Unit 1
PMU 1 I0 Mag...............................................
Metered zero-sequence current magnitude for Phasor
Measurement Unit 1
PMU 1 I0 Ang................................................
Metered zero-sequence current angle for Phasor Measurement
Unit 1
PMU 1 I1 Mag...............................................
Metered positive-sequence current magnitude for Phasor
Measurement Unit 1
PMU 1 I1 Ang................................................
Metered positive-sequence current angle for Phasor
Measurement Unit 1
PMU 1 I2 Mag...............................................
Metered negative-sequence current magnitude for Phasor
Measurement Unit 1
PMU 1 I2 Ang................................................
Metered negative-sequence current angle for Phasor
Measurement Unit 1