Once the phase-out process is completed, the component's state is either Fail or
Ready, depending on the argument markasfailed. If true, the phased-out component
is marked as a failed component (in order to replace the component). If false, the
phased-out component is in the Ready state.
Access Control:
User Category Permission
Storage administrator Disallowed
Storage integration administrator Disallowed
Application administrator Disallowed
Security administrator Disallowed
Read-only users Disallowed
Technicians Allowed
Completion Codes:
v PHASEOUT_NOT_SUPPORTED_FOR_THIS_COMPONENT_TYPE
This component type cannot be phased-out
v PHASEOUT_WILL_MAKE_SYSTEM_NON_REDUNDANT
Cannot phase out the component because it will cause data to be unprotected
v PHASEOUT_NOT_ALLOWED_IN_CURRENT_STATUS
Component cannot be phased-out in its current status
v COMPONENT_DOES_NOT_EXIST
Component does not exist
v COMPONENT_TYPE_CANNOT_BE_PHASED_OUT_AS_FAILED
Components of this type cannot be phased-out and marked as failed
v MODULE_CANNOT_BE_PHASED_OUT_DUE_TO_MANAGEMENT_
REQUIREMENT
Module cannot be phased out due to management requirement
Troubleshooting: Contact support
v CAN_NOT_PHASE_OUT_DISK_WITH_MARKASFAILED_NO
Disks cannot be phased-out with markasfailed=no
v COMPONENT_TYPE_MUST_BE_PHASED_OUT_AS_FAILED
Components of this type must be phased-out as failed
v USE_SERVICE_PHASEOUT_COMMAND
Command component_phaseout does not support services. Please use
service_phaseout.
v CONTAINING_COMPONENT_IN_WRONG_STATUS
Operation not allowed in current status of containing component.
v SUBCOMPONENT_IN_WRONG_STATUS
Operation not allowed in current status of a subcomponent.
v CONTROLLING_SERVICES_NOT_ALLOWED_FOR_USER_CATEGORY
Controlling services not allowed for user category
v NOT_ALL_PSUS_OK
There is one or more PSUs disconnected or failed, this may cause the requested
action to cause module failures