ECC800 Data Center Controller
User Manual (for ECC800-Pro)
5 Power-On Commissioning
Copyright © Huawei Technologies Co., Ltd.
111
Figure 5-12 PDU2000-M (H) communications settings
Press DOWN and UP to select the address to be set.
Press MENU to confirm the settings.
If modification is successful, is displayed: If modification fails, is
displayed:
Step 2 Add a PDU2000.
1. Log in to the ECC800-Pro WebUI as an administrator.
2. Add a PDU2000.
Table 5-13 Adding a PDU2000
Path
Parameter
Name
Setting
Choose System
Settings >
Device
Management
and click Add
Device. The
parameters for
adding devices
are displayed.
Device attribute
Select PDU from the drop-down list box.
Device type
Select PDU2000-M (C) or PDU2000-M (H) from
the drop-down list box based on the actual device.
Connect to
Select ETH Actuator1 from the drop-down list
box.
NOTE
The setting example indicates that the PDU2000 is
connected to the ETH Actuator1.
Communications
port
COM1/COM2
Device address
Enter the actual device address of the PDU2000.
3. Click Test Connect to check whether the PDU2000 connects to the ECC800-Pro
properly.
If the connection is normal, click Confirm. The connected devices are displayed in
the Number of connected devices list.
If the connection is abnormal, check whether the cable is properly connected to the
device, whether the device is running properly, and whether the parameter settings
are consistent with the device parameters.
----End