FusionModule2000 Smart Modular Data Center 
Installation Guide 
2 Installation Preparations 
 
Huawei Proprietary and Confidential                                     
Copyright © Huawei Technologies Co., Ltd. 
 
Precautions for Placing 
Place cardboard boxes in sequence based on their numbers. 
Figure 2-2 Arranging components 
 
 
2.2 Unpacking and Acceptance 
Context 
Unpack and inspect all cabinets, mechanical parts, and components. Check that all the items 
are intact and comply with the packing list on the presence of both the project supervisor and 
customer. 
Procedure 
Step 1  Unpack the carton labeled Contain Packing List and take out the Packing List. 
Step 2  Check all items against the Packing List. 
Step 3  If an item is incorrect or missing, contact Huawei technical support. 
Step 4  If any item is damaged, fill in the Cargo Replacement Application Form and report it.