FusionModule2000 Smart Modular Data Center
Installation Guide
15 Installing Monitoring Devices
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
235
15.9.1 Laying Out the Water Detection Cable (Dual-Row Scenario)
Context
Figure 15-77 Laying out a water detection cable (top pipe routing)
(1) ECC800
(2) Network cable
(3) Water detector
(4) Water detection cable