FusionModule2000 Smart Modular Data Center
Installation Guide
C Installation Verification
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
C Installation Verification
Cabinet Installation Checklist
The cabinets are placed according to the equipment room
layout diagram.
â–¡ Compliant â–¡
Incompliant
The height deviation of all cabinets and the depth
deviation of adjacent cabinets are less than 5 mm.
â–¡ Compliant â–¡
Incompliant
All bolts are tightened, especially the bolts used for
electric connection. Flat washers and spring washers are
installed properly.
â–¡ Compliant â–¡
Incompliant
The cabinet is clean and complies with dustproof
requirements.
â–¡ Compliant â–¡
Incompliant
The paint on the cabinet exterior is intact. If paint flakes
off, repaint that area to avoid corrosion.
â–¡ Compliant â–¡
Incompliant
The cabinet door and lock work properly.
â–¡ Compliant â–¡
Incompliant
All labels are correct, clear, and complete.
â–¡ Compliant â–¡
Incompliant
There is no foreign matter such as adhesive tape, cable
ties, paper, or packing materials left around the cabinet.
â–¡ Compliant â–¡
Incompliant
The cabinet filler panels are in proper positions so that
the cold aisle and hot aisle are isolated.
â–¡ Compliant â–¡
Incompliant
Aisle Containment Checklist
All components of the aisle containment are installed.
â–¡ Compliant â–¡
Incompliant
The end doors can be opened and closed smoothly.