FusionModule2000 Smart Modular Data Center
Installation Guide
C Installation Verification
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
C Installation Verification
Cabinet Installation Checklist
The cabinets are placed according to the equipment room
layout diagram.
□ Compliant □
Incompliant
The height deviation of all cabinets and the depth
deviation of adjacent cabinets are less than 5 mm.
□ Compliant □
Incompliant
All bolts are tightened, especially the bolts used for
electric connection. Flat washers and spring washers are
installed properly.
□ Compliant □
Incompliant
The cabinet is clean and complies with dustproof
requirements.
□ Compliant □
Incompliant
The paint on the cabinet exterior is intact. If paint flakes
off, repaint that area to avoid corrosion.
□ Compliant □
Incompliant
The cabinet door and lock work properly.
□ Compliant □
Incompliant
All labels are correct, clear, and complete.
□ Compliant □
Incompliant
There is no foreign matter such as adhesive tape, cable
ties, paper, or packing materials left around the cabinet.
□ Compliant □
Incompliant
The cabinet filler panels are in proper positions so that
the cold aisle and hot aisle are isolated.
□ Compliant □
Incompliant
Aisle Containment Checklist
All components of the aisle containment are installed.
□ Compliant □
Incompliant
The end doors can be opened and closed smoothly.