FusionModule2000 Smart Modular Data Center
Installation Guide
15 Installing Monitoring Devices
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
180
Figure 15-2 Connecting a device ground cable
15.1.1 (Optional) Installing an RH2288 Server
Preparations
Tool: Phillips screwdriver
Materials: RH2288 server, guide rail, rubber plug
Document: installation position diagram for monitoring devices in the network cabinet
Procedure
Step 1 Install guide rails.