FusionModule2000 Smart Modular Data Center
Installation Guide
15 Installing Monitoring Devices
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
15 Installing Monitoring Devices
15.1 Equipment Layout in the Network Cabinet
Diverse monitoring devices are available. Determine the installation plan based on the
configurations. Figure 15-1 specifies the installation positions for certain monitoring devices,
which are for reference only.
Figure 15-1 Equipment layout in the network cabinet
Relocate the cable manager in the rear door position as high as the device to be installed.
Use a flat-head screwdriver to insert floating nuts into the device mounting holes in the rack rails of
the network cabinet. Ensure that the floating nuts on both sides are on the same horizontal line.
Before connecting power cables for the device, use the ground cable delivered with the device to
connect from the device ground point to the cabinet ground point close to the device mounting holes,
as shown in Figure 15-2. When there is a special grounding requirement and a cabinet ground bar
can be deployed, use the ground cable prepared by the customer to connect from the device ground
point to the cabinet ground bar.