FusionModule2000 Smart Modular Data Center
Installation Guide
6 Installing the Network Cabinet, IT Cabinet, and Battery
Cabinet
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
64
Figure 6-6 Removing M8 screws
Step 2 Open the cabinet rear door, install the horizontal ground bar on the topmost position of the
rack rail (outside), and secure the ground bar using the M8 screws removed earlier.
Install the horizontal ground bar in the battery cabinet or IT cabinet adjacent to the PDC.
Figure 6-7 Installing a horizontal ground bar
----End
6.8 (Optional) Installing a Vertical Ground Bar
Context
Install the vertical ground bar in the IT cabinet that is closest to the PDC. The BOM number
of the vertical ground bar is 21241363.
Preparations
Tool: Phillips screwdriver
Material: vertical ground bar

Table of Contents

Other manuals for Huawei FusionModule2000

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei FusionModule2000 and is the answer not in the manual?

Huawei FusionModule2000 Specifications

General IconGeneral
BrandHuawei
ModelFusionModule2000
CategoryStorage
LanguageEnglish

Related product manuals