FusionModule2000 Smart Modular Data Center
Installation Guide
C Installation Verification
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
The gap between end doors is even.
□ Compliant □
Incompliant
After the end door is closed, the rubber strip in the
middle seals the gap properly.
□ Compliant □
Incompliant
After the double revolving door is closed, the height
deviation of the two door panels is less than 5 mm.
□ Compliant □
Incompliant
The rotating skylights work smoothly.
□ Compliant □
Incompliant
The end planes of skylight connective plates are flush
with each other.
□ Compliant □
Incompliant
The skylight electromagnet firmly suctions the skylight
when the power is on, and the skylight drops naturally
when the power is off.
□ Compliant □
Incompliant
All labels are correct, clear, and complete.
□ Compliant □
Incompliant
There is no foreign matter such as adhesive tape, cable
ties, paper, or packing materials left in and around the
aisle.
□ Compliant □
Incompliant
Cable Installation Checklist
All cable joints are secured properly, especially the cable
joints between network cables and cables inside cabinets.
□ Compliant □
Incompliant
Exposed parts near the wiring terminals and lugs are
wrapped with PVC insulation tape or heat shrinking
tubing.
□ Compliant □
Incompliant
All wiring terminals are securely installed with flat
washers and spring washers and are in good contact.
□ Compliant □
Incompliant
Cables are bound neatly, and cable ties are secured
evenly and properly in the same direction.
□ Compliant □
Incompliant
Cables are routed in a way convenient for maintenance
and capacity expansion.
□ Compliant □
Incompliant
All labels at the cable ends are clear.
□ Compliant □
Incompliant
Excess sections of cable ties are neatly cut.
□ Compliant □
Incompliant
There is no unnecessary adhesive tape or cable tie on