FusionModule2000 Smart Modular Data Center
Installation Guide
C Installation Verification
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Electric Installation Checklist
All ground cables are copper cables with diameters
meeting the requirements. No switch or fuse is
installed at the middle of a ground cable, and no
short-circuit occurs.
â–¡ Compliant â–¡ Incompliant
Ground cables, AC input power cables, and
internal cables are connected in accordance with
the circuit diagram and screws are secured. No
short-circuit occurs on power inputs or outputs.
â–¡ Compliant â–¡ Incompliant
Power cables and ground cables are not coiled and
extra parts are cut off.
â–¡ Compliant â–¡ Incompliant
Lugs for power cables and protective ground
cables are soldered or crimped securely.
â–¡ Compliant â–¡ Incompliant
Power cables and ground cables are routed and
bundled separately from other cables.
â–¡ Compliant â–¡ Incompliant
Batteries are free from damage, cracks, and bulges.
â–¡ Compliant â–¡ Incompliant
Batteries are neat and do not leak electrolyte.
â–¡ Compliant â–¡ Incompliant
Wiring terminals of batteries are free from
damage, break, and acid leakage.
â–¡ Compliant â–¡ Incompliant
Battery safety valves are intact, without leakages.
â–¡ Compliant â–¡ Incompliant
Battery cables are correctly connected, and the
terminal voltages of battery strings are normal.
â–¡ Compliant â–¡ Incompliant
DIP switches on devices are correctly set.
â–¡ Compliant â–¡ Incompliant
Customer signature:
Check date: