FusionModule2000 Smart Modular Data Center
Installation Guide
6 Installing the Network Cabinet, IT Cabinet, and Battery
Cabinet
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
60
Figure 6-2 Installing a floating nut
Step 2 (Optional) Remove side plates based on the labels on the side plates to be adjusted.
Step 3 Secure each side plate to the outer side of the end cabinet.
Install two side plates for each end cabinet, one in the upper part and the other in the lower part.
Figure 6-3 Installing a cabinet side plate
Step 4 (Optional) After adjusting side plates, remove the labels on the plates.
----End