FusionModule2000 Smart Modular Data Center
Installation Guide
6 Installing the Network Cabinet, IT Cabinet, and Battery
Cabinet
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Figure 6-4 Taking out industrial connectors
Step 2 Lay out the industrial connectors and cables on the cabinet top, and reinstall the rodent-proof
mesh.
Cut the rodent-proof mesh based on the cable thickness using diagonal pliers. If the opening is
too large, unwanted things may fall into the cabinet through the opening.
Figure 6-5 Laying out industrial connectors and cables
----End