FusionModule2000 Smart Modular Data Center
Installation Guide
8 Combining Cabinets
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
85
Do not remove the anchor bolts. Otherwise, rework is required if the cabinet height does
not meet requirements.
Anchor bolt adjustment method: Wrench an anchor bolt clockwise to elevate a cabinet, or
wrench an anchor bolt anticlockwise to lower it. Anchor bolts can be adjusted within a
range of 08 mm.
Put a level at the bottom of the cabinet in width and depth directions and check that the air
bubble is in the middle between the two lines marked on the glass tube.
Figure 8-2 Leveling a cabinet
(1) Level
Step 3 (Optional) Secure cabinets on the bases.
Perform this step if bases are required.
For the PDC, network cabinet, IT cabinet, 600 mm wide air conditioner, and 300 mm
wide M-type air conditioner:
a. Install the spring washers, flat washers, and insulation coverings on the bolts.
b. Use an M20 torque wrench to tighten the four bolts in diagonal order.

Table of Contents

Other manuals for Huawei FusionModule2000

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei FusionModule2000 and is the answer not in the manual?

Huawei FusionModule2000 Specifications

General IconGeneral
BrandHuawei
ModelFusionModule2000
CategoryStorage
LanguageEnglish

Related product manuals