Trainee Guide TR-L2-M2000
Level 2 Maintenance Training – M2000 Dispensing Systems 1-2-24 P/N 73-0018-00 (Revision B)
Information Sheet 1-5-1
Proper Powering On Procedures
A. Connecting to Facilities
1. Connect the Main Power Cord from the Main Power Inlet to the facility power
source.
2. Connect the Main Air to the facility air supply.
3. Proceed to Section B (Service Startup).
B. Proper Powering On Procedure
1. Make sure that all EMO buttons are disengaged. If they are engaged, turn
clockwise until the button pops out.
2. Turn the Main Power Switch ON.
3. Press Start on the front control panel.
4. Make sure that the computer and monitor are on and that Windows is running.
C. Operator Startup
1. Perform steps above under
Connect to Facilities
and
Proper Powering On Procedure
.
2. Close any open programs.
3. Start Fluidmove by double-clicking on the FmNT icon.
4. In the Main window, click on Run a Program.
5. In the Programming window, click on Setup.
6. Click on Prompted Setup.
7. Follow the on-screen prompts.
 Refer to the
FmNT User Guide
or the Online Help for assistance if necessary.
8. In the Programming window, click on Load.
9. Select the program you wish to run, and click on OK.