Trainee Guide TR-L2-M2000
Level 2 Maintenance Training – M2000 Dispensing Systems 4-2-49 P/N 73-0018-00 (Revision B)
Outline Sheet 4-13-1
Testing the I/O Functions of the Dispenser and Conveyor
A. Introduction
When troubleshooting the dispensing system, it may be necessary to test the input and
output (I/0) functions of the Dispenser and Conveyor.
B. Enabling Objective
4.13 Perform procedure to list and test the I/O functions of the Dispenser and
Conveyor.
C. Topic Outline
1. Introduction
2. Overview
 Testing I/O Functions
 Conveyor I/O Test
 Dispenser I/O Test
3. Summary and Review