S0607080K
Page 49
Transmission and Torque Converter
(ZF 4WG-310)
8. Loosen socket head screws and remove
cover.
9. Remove opposite cover.
10. Demount pressure regulator and remove
cable harness.
11. Loosen socket head screws, remove
retaining plates and demount pressure
regulator.
12. Loosen two socket head screws and locate
the housing provisionally using adjusting
screws. (Housing is spring-loaded). Now,
loosen the remaining socket head screws.
Figure 47
Figure 48
Figure 49
Figure 50