FusionModule2000 Smart Modular Data Center 
Installation Guide 
3 Smart Module Layout Requirements 
 
Huawei Proprietary and Confidential                                     
Copyright © Huawei Technologies Co., Ltd. 
 
Figure 3-10 Column in the aisle containment (A < 800 mm) 
 
 
 
Cabinet places on the column side are left blank and sealed by sealing plates. Directions of the 
concave sides of the sealing plates are shown in Figure 3-10. 
 
Install cable trays over the cabinets on both sides of the blank cabinet places for routing 
strong-current and weak-current cables. 
 
Install an adjustable skylight over the aisle containment. The area to be covered by the adjustable 
skylight is shown in Figure 3-10.