FusionModule2000 Smart Modular Data Center
Installation Guide
4 (Optional) Installing Bases
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Table 4-1 Specifications of bases with adjustable dimensions
Height (adjustable): 270–410 mm; depth
(adjustable): 1000 mm, 1100 mm, or 1200
mm
Height (adjustable): 410–700 mm; depth
(adjustable): 1000 mm, 1100 mm, or 1200
mm
Height (adjustable): 270–410 mm; depth
(adjustable): 1000 mm, 1100 mm, or 1200
mm
Height (adjustable): 410–700 mm; depth
(adjustable): 1000 mm, 1100 mm, or 1200
mm
Height (adjustable): 270–410 mm; depth
(adjustable): 1000 mm, 1100 mm, or 1200
mm
Height (adjustable): 410–700 mm; depth
(adjustable): 1000 mm, 1100 mm, or 1200
mm
Preparations
Tools: ruler, marker, torque wrench, Phillips screwdriver, right angle, hammer drill, φ16 drill
bit, level
Materials: base and accessories, expansion bolt, base connecting plate, washer, floor holder
Document: base installation position diagram
Procedure
Step 1 Adjust the base height.
1. Measure the distance (H) between the concrete floor and the upper surface of the ESD
floor using a ruler and record the value of H.