Transport
7.2 Transport by ship
Operating manual 3 302 819 en 7 - 5
GMK3060
13.12.2018
7.2 Transport by ship
• Secure the truck crane with the chocks (1).
• Fasten the lifting gear to the slinging points (2)
on both sides. Ensure that no attachments,
cables or hoses are damaged in this process.
Additional slinging points are usually necessary
when the truck crane is transported on a ship.
Ensure that the specified values are not
exceeded when doing this.
• If necessary, use additional points as slinging
points.
G
Risk of accidents due to falling parts!
Use only suitable lifting gear with sufficient load bearing capacity and use only
the slinging points provided.
1 Main boom head: 50 daN
2 Main hoist: 50 daN