Rigging work
12.1 Rigging work checklists for crane operation with the main boom
Operating manual 3 302 819 en 12 - 1
GMK3060
13.12.2018
12 Rigging work
If the truck crane on the site has already been rigged, proceed according to the
CHECKLIST: Checks before operating the crane, p. 11 - 1.
12.1 Rigging work checklists for crane operation with
the main boom
H
This checklist is not a complete operating manual. There are accompanying
operating instructions which are indicated by cross-references.
Observe the warnings and safety instructions there!
12.1.1 CHECKLIST: Rigging
1. Choose a suitable site; à Selecting the suitable site, p. 12 - 9.
2. Check that the parking brake is engaged – if necessary, engage the parking
brake.
H
The following points only apply to rigging in Free on wheels operating position.
Continue the checklist at point 7. when rigging the truck crane on outriggers.