Rigging work
12.1 Rigging work checklists for crane operation with the main boom
12 - 6 3 302 819 en Operating manual
GMK3060
13.12.2018
12.1.2 CHECKLIST: Unrigging
H
This checklist is not a complete operating manual. There are accompanying
operating instructions which are indicated by cross-references.
Observe the warnings and safety instructions there!
1. With the rigging mode set correspondingly, unrig the counterweight;
à CHECKLIST: Unrigging the counterweight, p. 12 - 58.
2. Enter and confirm the current rigging mode with the new rigged counter-
weight combination;
à Entering the rigging mode, p. 11 - 36.
3. Depending on transport:
– Attach the hook block to the bumper;
à p. 12 - 78 or
– Set down the hook block and unreeve the hoist rope;
à Setting down the hook block, p. 12 - 80
à Unreeving the hoist rope, p. 12 - 88
4. Retracting the main boom;
à p. 11 - 95.
5. – Turn the superstructure to the 180° position to the front with the RCL set
accordingly,
– Set down the main boom on the boom rest.
– Lock the turntable;
à p. 11 - 18.