Rigging work
12.7 Rigging work on the main boom
12 - 82 3 302 819 en Operating manual
GMK3060
13.12.2018
12.7.3 Reeving and unreeving the hoist rope
You must reeve a certain number of rope lines, depending on the required load
bearing capacity. Four reeved rope lines correspond, for example, to 4-fall
reeving;
à Possible reeving methods on the main boom, p. 12 - 89.
To reeve and unreeve the hoisting rope, you must remove the pocket lock.
After reeving you must reattach the pocket lock.
There are A or B versions.
Version A
Removing
• Pull the pin (2) out and remove the fork
element (1).
• Slide the holder (3) back and remove it from
the hoist rope (4).