Rigging work
12.1 Rigging work checklists for crane operation with the main boom
Operating manual 3 302 819 en 12 - 5
GMK3060
13.12.2018
20. Install anemometer and if necessary air traffic control light;
à Anemometer and air traffic control light, p. 12 - 101.
21. Install the camera on main boom if required;
à Cameras for crane operation, p. 12 - 106.
22. Fold out and adjust all mirrors for crane operation;
à p. 12 - 105.
23. Perform all the required checks prior to crane operation;
à CHECKLIST: Checks before operating the crane, p. 11 - 1.
24. Enter and confirm the current rigging mode;
à Entering the rigging mode, p. 11 - 36.
25. With the rigging mode adjusted accordingly, rig the counterweight combina-
tion required for the operation according to Lifting capacity table;
à CHECKLIST: Rigging the counterweight, p. 12 - 56.
26. Enter and confirm the current rigging mode with the new rigged counter-
weight combination;
à Entering the rigging mode, p. 11 - 36.