Step 2B: Running the Continuity Test (Recommended)
1-20 72A-1898 Rev. A 11/01
Monday, November 26, 2001 1:09 pm
Step 2B: Running the Continuity Test (Recommended)
Figure 1.15 shows the initial Continuity Test window.
N
OTE
The Continuity Test must be run with the circuit breaker in the closed
position.
If the Continuity Test fails, check all test connections starting with the
connections to the circuit breaker, then the connections to the TDR9000
Physical Front Panel.
For instructions on performing this test, refer to ”Running the Continuity
Test” on page 4-71.
Figure 1.15 Continuity Test