DIRECTION 5394141, REVISION 5 LOGIQ™ P5 SEVICE MANUAL
Section 4-9 - Board Function Checks 4-53
4-9-13 Transbox Assy Function Validation Procedure
1.) Turn on the system. Refer to 3-5-1 "Power On/Boot Up" on page 3-11 for power up sequence to
check AP950 Assy function. The system must show correct operation as described on sequence.
2)Check the peripheral operation. Refer to Section 4-5 "Peripheral Checks" on page 4-26 to confirm the
peripheral operation. All peripheral must work correctly as described Section 4-5.
4-9-14 Fuse set Function Validation Procedure
1.) Turn on the system. Refer to 3-5-1 "Power On/Boot Up" on page 3-11 for power up sequence to
check Transbox Assy function. The system must show correct operation as described on sequence.
2.) Check the peripheral operation. Refer to Section 4-5 "Peripheral Checks" on page 4-26 to confirm
the peripheral operation. All peripheral must work correctly as described Section 4-5.
4-9-15 ARP Assy Function Validation Procedure
1.) ARP Assy function can be validated by the result of 'Peripheral Test'. Once ARP Assy is replaced,
do peripheral test in order to confirm the successful installation. Refer to the Section 4-5 "Peripheral
Checks" on page 4-26.
4-9-16 ASIG ASSY Function Validation Procedure
1.) Turn on the system. R
2.) Check the basic function of system's different modes. Refer to 4-3-4 "System B/M-Mode Checks"
on page 4-8 and Refer to 10-5-2-1 "System Checks" on page 10-8.