3 — Installation verification
9
Operator Manual
Vision® 1300 Series
920515770_J
• Temperature of 41 to 104°F (5 to 40°C);
• Maximum relative humidity is 80% for temperatures up to 88°F (31°C) decreasing linearly to 50% relative
humidity at 104°F (40°C);
• Pollution Degree 2.
Pollution degree 2: Equipment must be installed in an environment where normally only non-conductive pollution
occurs but where occasional, temporary conductivity caused by condensation can be expected (as determined according
to International Standard EN/IEC 61010-1, Second Edition).
3.6 Installation Verification
An equipment drawing showing all the utility and space requirements was sent after the order for this equipment was
received. The clearance space specified on the equipment drawing is necessary for proper installation, operation and
maintenance of the washer/disinfector. Uncrating/Installation Instructions are provided with the washer/disinfector. If
these documents are missing or misplaced, contact STERIS, providing the serial number and model of the
washer/disinfector. Replacement copies will be sent promptly.
After installing the equipment according to the Uncrating/Installation Instructions, complete the following checklist to
help ensure complete and correct installation, or contact STERIS to schedule a service technician to test your
installation and demonstrate proper equipment operation.
◻ Disconnect switches (not provided by STERIS), capable of being locked in OFF position for maintenance purposes,
are installed in electrical supply lines near the washer/disinfector and in compliance with occupational health and
safety regulations, as well as electric codes. Disconnect switches must bear the identification of the equipment to
which they are connected.
NOTE: If washer/disinfector is installed next to other equipment, disconnect switches should be located so
service can be shut off to one piece of equipment at a time.
◻ Washer/disinfector is positioned as shown on equipment drawing, with required clearance space and in relation to
building supply lines.
◻ Washer/disinfector is leveled.
◻ Electrical supply for washer/disinfector is as specified on equipment drawing.
◻ Building hot water line supplies water to washer/disinfector as specified on equipment drawing. Hot water
pressure must be within specifications on equipment drawing.
◻ Building cold water line supplies water to washer/disinfector as specified on equipment drawing. Cold water
pressure must be within specifications indicated on equipment drawing.
◻ If Pure Water Line option is present: Building pure water line supplies water to washer/disinfector as specified on
equipment drawing. Pure water pressure must be within specifications indicated on equipment drawing.
◻ If steam-heated washer/disinfector: Building steam line provides steam to washer/disinfector as specified on
equipment drawing. Steam pressure must be within specifications indicated on equipment drawing.
◻ If steam-heated washer/disinfector: Building condensate return line is connected to washer/disinfector as
specified on equipment drawing. Condensate return line must be within specifications indicated on equipment
drawing.
◻ Building compressed air supply to washer/disinfector is as specified on equipment drawing. Compressed air
pressure must be within specifications indicated on equipment drawing.
◻ Washer/disinfector drain line is positioned relative to pit drain opening as specified on equipment drawing.
◻ Washer/disinfector is connected to building ventilation system as specified on equipment drawing. Building
ventilation must be within specifications indicated on equipment drawing.
◻ Spring for emergency stop cables are correctly installed on microswitch
◻ Switches for Emergency Stop pushbutton, located on control panel are correctly installed on soiled and clean side.
◻ Inspect doors for alignment and smooth movement.