Rigging work
12.1 Rigging work checklists for crane operation with the main boom
Operating manual 3 302 819 en 12 - 3
GMK3060
13.12.2018
8. Deactivate (Lock) the suspension – symbol red (suspension off);
à p. 5 - 17.
9. Support the truck crane with the outrigger span required for the job according
to the Lifting capacity table and raise until none of the wheels is touching the
ground;
à Operating the outriggers, p. 12 - 27.
10. Align the truck crane horizontally.;
à p. 12 - 43.
11. Switch off the engine;
à In the driver's cab, p. 4 - 19,
à On the outrigger control units, p. 4 - 19.
12. Earth the truck crane, if necessary;
à Earthing the truck crane, p. 12 - 13.
13. Inspect the truck crane, while looking out in particular for any leaking fluids
(oil, fuel or water).