3 Operation and Test Run
3 - 24
High-function General-purpose Inverter 3G3RX-V1 User’s Manual (I578-E1)
3-4 Flow of Test Run
Perform a test run of the inverter according to the following flow.
Item Description
Reference
Installation Install the inverter according to the installation conditions. Section 2,
2-1
Wiring and
connections
Connect the inverter to the power supply and peripheral equipment. Section 2,
2-3
Power-on Check the points mentioned in the next page before turning on the
power supply.
Section 2,
2-3
Display status
checks
Check that there is no error in the Inverter. Section
10
Parameter
Initialization
Initialize the inverter parameters. Section 5,
5-1
Parameter setting Set the parameters required for the test run. Section 5,
5-3, 5-4
No-load run Run the motor with no-load via the Digital Operator. Section 3,
3-1
Load run Run the motor via Digital Operator, with the mechanical system
connected.
Section 3,
3-1
Operation
Basic settings (operation with the basic settings required to operate
and stop the inverter.)
Section 5
Vector control (operation the inveter with the vector control and other
functions.)
Section 6