Maintenance
Carrying out final maintenance work
30
164 | 188
Building Technologies
009052_s_en_
--
Fire Safety
2016
-
-
02
Function Activity Interval
(years)
1 2 5
Alarm organization Check the function of the delay times t1 and t2. X
Activate a global alarm with an 'Automatic detector' in the
'Unmanned operation' operation mode.
X
Activate a local and global alarm by setting a 'Manual call point' to
the 'Manned operation' and 'Unmanned operation' operation
modes.
X
Check automatic switchover from 'Manned operation' to
'Unmanned operation' on the basis of the event memory entries.
X
Check activation of the remote transmission equipment with
'ALARM'.
X
Actuate the corresponding danger level by activating a detector
with the detector exchanger and tester or intelligent detector tester.
X
Table 8: Intervals for the function test
30.11 Carrying out final maintenance work
1. Activate a test alarm through the system operator with remote transmission.
2. Issue subsequent instructions if necessary.
3. Ensure that the system file is available and up to date.
4. Update the system data when the central configuration is changed. Archive a
copy with the 'Site' and a copy in the office.
5. Check the master data sheet (phone no., contact person, etc.).
6. Replace all used material.
7. Cancel all blockings and 'OFF' statuses.
8. Have the revision confirmed by the system owner.