Detailed commissioning steps
Preparing 'Station' for commissioning
21
77 |
Building Technologies
21.2 Preparing 'Station' for commissioning –without BDV
installation
1. Connect the cables for the ↑ detector lines and the peripheral devices.
2. Connect the power supply (mains and batteries).
The ↑ 'Station' starts and reads in the internal hardware.
During start-up, the 'FAULT' LED flashes and the display shows the
progress.
During start-up, the firmware version F-FXS2001 is displayed.
3. Wait until the display indicates the selection of the ↑ BDV.
The 'Station' is prepared for commissioning.
It is not necessary to install the BDV for the further procedure. This saves having
to restart the ↑ 'Station'.
Following preparation, you can for instance perform the following steps, depending
on the selected commissioning variant:
● Initialize the ↑ 'Station'
● Auto-configure the 'Station'
● Load the configuration from the PC to the 'Station'