Building Technologies
11 Commissioning FG2020
Because of the fact that the FG2020 has no integrated operating unit, you must
configure at least one operating unit within the 'Site' in such a way that it has a
↑ visibility of the FG2020.
Commissioning
1. Create a 'SintesoWorks' and the ↑ 'Site' in Stations and pre-configure, if
required.
2. Configure the visibility of the FG2020 in SintesoWorks. You will find information
on this in the following chapter.
3. Follow the commissioning steps in chapter 'C- Commissioning networked
'Stations' [➙ 43]'.
Configuring ↑ visibility on FG2020
Figure 3: Assigning a visibility
ϖ The 'FG2020' element is created.
ϖ The 'Stations' that are to have a visibility of the SIGMASYS/D100 control panel
are created.
1. Select the 'Operation' task card.
2. In the tree view, open the 'Station' that is to have a visibility of the
SIGMASYS/D100 control panel.
3. Open the 'PMI' window and highlight the 'Standard visibility' element.
4. In the menu bar, click on 'Assign'.
The 'Assign dialog' window opens.
5. Select the desired visibility on the left in the window.
6. On the right in the window, select the corresponding element.
7. Click on 'Assign'.
The element is assigned with 'Standard visibility'.