Changing and expanding the FDnet/C
Extending the detector line to include additional devices
14
49 |
Building Technologies
14 Changing and expanding the FDnet/C-NET
detector line
14.1 Extending the detector line to include additional
devices
NOTICE
Incorrect assignment between detector/detector zone and customer text
Inaccurate messages in the event of an alarm
● You must not change the FDnet topology at the same time as adding extra
devices.
● After extending or changing a ↑ 'Site' always run a test to check the
assignment between detector/detector zone and customer text.
find additional information about the individual steps on the specified
pages.
1. Switch the FDnet detector line off. Link [➙ 82]
2. Mount and wire the new devices. Link [➙ 49]
3. Read-in the FDnet devices. Link [➙ 85]
4. Connect the PC to the ↑ 'Station'. Link [➙ 27]
5. Load the configuration from the 'Station' to the PC. Link [➙ 32]
6. Configure the new devices. Link [➙ 50]
7. Load the configuration from the PC to the 'Station'. Link [➙ 30]
8. Test the function of the 'Site'. Link [➙ 91]
9. Remedy any errors you notice and load the corrected configuration from the
PC to the 'Station'. Link [➙ 30]
10. Disconnect the PC from the 'Station'. Link [➙ 27]
14.1.1 Mount and wire new devices
During an extension of the line, all possible wiring work on the bases must be
carried out from devices that have already been localized. When replacing these
devices, these must be re-inserted in exactly the same place (observe the serial
number).
1. Remove these devices from their bases.
2. Mount and wire the new devices, like bases.
3. Insert the new devices into the new bases and write down the serial numbers
on the layout plan.